Just an example of the things I'm tracking that need to be done:


2/26 Fire valve on outside of garage. Status? Also need trimout
2/26 Roof at balcony on roof- needs flashing and trim.
2/26 Center light at front door. This needs to be done so it can be painted.
2/26 Electrician- outlet in bedroom for train that is covered up. Speaker wires in kitchen and outside.
2/26 Chimmney caps, sizes, prices, etc.
2/26 Status on slab at garage?
2/26 Price on concrete drive and asphalt. I think we will go with all asphalt.
2/26 Waterproofing stucco on window wells (Doug to provide) Material that rick started with seem to fall off?
2/26 Who/when on backfilling window wells. (wait for Brian to paint)
3/5 Roof on barn where it is popping up
3/5 Estimate on outside railings. When can your steel guy give me an estimate on all this?
3/12 Install blower on roof.
3/18/2007-Stucco to be consistent at ground grade on West of hoiuse in courtyard area.
Status on mirrors and shower doors.

Open items for Pete & Todd:
Trim piece at balcony
Trim mirrors (same as windows-- space between bottom trim and top of soapstone counter).
Center light at balcony
Trim master ceiling
Trim corner toe kick at master bench seat
Door and bath hardware
Modify doors of antique vanity
Open items for stone:
Brick at FP and stove, stone hearth
Finish stone and window wells
Stone step
Steel:
Balcony, window wells, stairs, entry gate and wing fence
Painter:
Inside
Shed, playhouse, well house
Touch up outside barn room and trim
Window wells
Downspouts, Flashing and mechanical on rood
Electrical trimout-Let me know when lights should be put out.
Plumbing- no brazen bronze. Install booster pump (test first). Is recirc pump installed?
Would like faucets for island asap.
Misc:
Security system trimout
Fire System Trimout
Touch up paint on cabinets from Hellers
Moros- any remant of Soapstone- can we have? I think we need to add backspalsh to bake center.

Update stone & paint

The stone masons (two guys working the last two days) are making progress and it's about 3/4 of the way done.

Painters are ready to spray the main floor (primed and prepped). It's been about 3 weeks tomorrow on the inside-- what he figured. A crew of around 3-5 people at a time. There will still be a lot of touch up I'm sure.

Pete and Todd are coming by Saturday for a couple of small items (light over outside entry needs to be centered, trim at master ceiling, trim at toe kick on bench seat in master).

The electricians had to wire the front steps before they could pour concrete, but they did that and now the concrete is poured, forms are off and it all looks good. The electricians put outlets and switches in the basement and upstairs and put up the exterior lights, but ran out of work for now.

The next steps are trim electrical, install counters (tomorrow?), install remaining cabinets in laundry and niches (tomorrow), install plumbing fixtures, sand and finish hardwood with one coat, finish trim out, install appliances, finish last coat on hardwood and install carpet and clean.

I still need to get the window well, stair and balcony railings ordered (comparing bids), teh front gate ordered and installed, and find a landscaper. We are also waiting on the asphalt-- they don't open until late spring.

Tuesday, March 20, 2007

Paint and stone

The stone work continues (1 guy, not the 30 Rigo talked about) and they are making good progress and we love the stone. The fence builders have also got a lot done and are very good guys.

Painters are about done with the basement and upstairs and are done priming the main floor so they should be wrapping up in a few days.

The copper roof at the office bay was put on today and looks great.

Electricians are starting to trim out the outlets, etc. By next week we should be able to get a lot of electrical and plumbing done. Countertops are supposed to be here this week.