No Internet, but work continues
If you noticed the lack of video it's not you. Pathbroadband has been down for a week now. A company wide outage. Maybe they are going out of business? There voice mail says it will be up tomorrow. We'll see.
Pete and Todd continue to plug along. We keep adding more work. The latest is a window seat in the sitting area of the master bedroom. They have a few weeks left by my guess-- built in at kitchen, mudroom and master should be about a week and a half, the stairs about a week, the beams and ceiling in the entry about a week and the fireplace a few days.
The tile guy should have been back at it today. Floors should be done soon.
Cabinets to be repainted Saturday. Countertops installed in the kitchen next Wednesday. The rest of the cabinets next Friday.
Then we'll need countertops for the vanities templated. Painting can maybe start in a week upstairs.
The outside is at a standstill over weather. I did decide to go with caissons for the front step. Waiting for an estimate on that.
Pete and Todd continue to plug along. We keep adding more work. The latest is a window seat in the sitting area of the master bedroom. They have a few weeks left by my guess-- built in at kitchen, mudroom and master should be about a week and a half, the stairs about a week, the beams and ceiling in the entry about a week and the fireplace a few days.
The tile guy should have been back at it today. Floors should be done soon.
Cabinets to be repainted Saturday. Countertops installed in the kitchen next Wednesday. The rest of the cabinets next Friday.
Then we'll need countertops for the vanities templated. Painting can maybe start in a week upstairs.
The outside is at a standstill over weather. I did decide to go with caissons for the front step. Waiting for an estimate on that.