Boulder Custom Home

Watch a custom home be built from the ground up.

Name: Andrew Batson

Friday, December 01, 2006

Slow progress on the drywall

It's been a while since an update, but progress has been relatively slow. The drywallers finally started around 11/23, but were only on the job for a day or two. They worked Monday and Tuesday this week, but it was cold with a big snowstorm so they were gone Wed and Thursday. They were back today. All told I think they have put in about three full days, and it is a crew of 3-4 guys. They have another couple days to go hanging the drywall. Then about another week and a half to tape and texture.

The furnaces are all now operating so hopefully the weather won't slow down any inside work. We do need a warm up to finish the outside stucco. I'm glad we started the house when we did or it seems like we would have a lot of slow downs due to weather.

Electricians continued to work on the garage rewire.